The CIP Division also oversees the Child Safety Fund which is designed to provide sidewalks complying with the sidewalk policy and school zone flashing warning signals in public school zones. To find out if your area meets the criteria for either of these programs, please click Sidewalk Policy or School Zone Flashing Warning Signals for the program’s requirements.
In 2007, Precinct 4's CIP division monitored more than 35 projects in the design phase with an estimated construction value of $145,691,564. As of December 31, 2007, 14 CIP projects with an estimated cost of $55,254,258 were under construction and six projects valued at $25,386,153 were completed in 2007. The total construction value of the 20 projects either completed and initiated in December 2007 has a combined value of $80,640,411.