A complete listing of Capital Improvement Projects.
| Project Name | Limit From | Limit To | Keymap | Internet Notes |
|---|---|---|---|---|
| Atascocita Rd at Atasca Oaks Dr | 337X | TS&II 2007 Package VI includes (4) intersections: 1) Atascocita at Atasca Oaks Drive, 2) Atascocita at Atascocita Meadows, 3) Will Clayton Parkway at Atascocita and 4) West Little York at Guhn Road. Project is currently in the bidding phase for construction purposes. (Last Updated On 12/28/2009) | ||
| Atascocita Rd at Atascocita Meadows Dr | 376D | TS&II 2007 Package VI includes (4) intersections: 1) Atascocita at Atascocita Meadows, 2) Atascocita at Atasca Oaks Drive, 3) Will Clayton Parkway at Atascocita and 4) West Little York at Guhn Road. Project is currently in the bidding phase for construction purposes. (Last Updated On 12/28/2009) | ||
| Birnamwood Dr | North of Cypresswood Dr | Spring Creek Dr | 293T 293P | Proposed improvements include installation of a 4-lane concrete boulevard section, storm sewer system, drainage mitigation, traffic control devices as warranted and all appurtenances necessary for realizing a complete project within a 100-foot right of way. Project is currently in the Study and Report phase. (Last Updated On 1/13/2010) |
| Boudreaux Rd | 2500 ft W of S Hwy 249 | 3500 ft E of S Hwy 249 | 328C 328D 288Z | Extension and realignment including construction of transitions to ultimate intersection. Construction is contingent on installation of TxDOT's SH 249 main lane improvements that have been indefinitely delayed, by TxDOT. (Last Updated On 8/12/2009) |
| Champion Forest | Spring Cypress Rd | Boudreaux Rd | 329H | Proposed improvements include upgrading the existing half-boulevard section to a 4-lane concrete boulevard including installation of traffic signal systems as warranted. Project is currently in the preliminary engineering phase and our goal is to request Commissioners' Court authorization to bid in the 3rd quarter of 2010. (Last Updated On 12/28/2009) |
| Cypresswood Dr | Homestead Pass Dr | James C. Leo Dr | 293U | The Cypresswood Drive sidewalk improvements are currently in the engineering design phase. (Last Updated On 8/17/2009) |
| East Richey Rd | East Hardy Rd | Aldine Westfield Rd | 333W 333T 333U | Proposed improvements include combination 4-lane concrete boulevard section or 5-lane concrete pavement section with storm sewer system. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid this project in the 1st quarter of 2010. (Last Updated On 12/28/2009) |
| Ella Blvd - 1 | Gears Rd | Rushcreek Dr | 372K | Installation of a 4-lane concrete boulevard section with storm sewer system including bridge over Greens Bayou. Project was awarded to Conrad Construction and construction activity commenced January 11, 2010 and is scheduled for construction completion by January 5, 2011. (Last Updated On 1/22/2010) |
| Ella Blvd - A | Louetta Rd | Spring Cypress Rd | 291Y | Proposed widening to a 4-lane boulevard section including the northbound bridge over Seals Gully and installation of sidewalks on the east side of Ella Boulevard between Sapling Trail and Spring Cypress Road. Harris County obtained Commissioners' Court approval to bid the improvements on January 12, 2010. The bidding and subsequent award process takes 90-120 days to accomplish. (Last Updated On 1/13/2010) |
| Ella Blvd - B | Spring Cypress Rd | Falvel Rd | 291Y | Proposed widening to a 4-lane boulevard section including the installation of missing sidewalk segments on the east and west side of Ella Boulevard between Spring Cypress Road and Falvel Road. Project was awarded to R. Hassel & Company and is currently in the construction phase. Construction activity commenced September 8, 2009 and is scheduled for construction completion by February 5, 2010. (Last Updated On 9/16/2009) |
| Fallbrook Dr - A | Old Bammel N Houston Rd | Antoine Dr | 371W | Installation of a 4 lane concrete boulevard section, storm sewer system, drainage mitigation, sidewalk improvements and traffic signals or traffic signal modifications. Project is currently in the engineering design phase and our goal is to bid this project in the 1st quarter of 2010. (Last Updated On 12/2/2009) |
| Fallbrook Dr - B | Antoine Dr | E of Halls Bayou | 411B | Widen to a 4-lane concrete boulevard section, with a bridge over Halls Bayou, storm sewer system, sidewalks on the north side of Fallbrook Drive and traffic control devices as warranted. Project is in the engineering design phase and our goal is to bid the project in the 4th quarter of 2010. (Last Updated On 12/29/2009) |
| Fallbrook Dr - C | East of Halls Bayou | Veterans Memorial Dr | 411C | Widen to a 4-lane concrete boulevard section, with storm sewer system, sidewalks on the north side of Fallbrook Drive and modifications to the existing pedestrian signal system. Project is currently in the engineering design phase and our goal is to bid this project in the 1st quarter of 2010. (Last Updated On 12/29/2009) |
| Falvel Rd - 1 | Ella Blvd | FM 2920 | 291U | Proposed upgrade from the 2-lane asphalt roadway to a 4-lane concrete boulevard section including the appropriate traffic signal modifications and intersection improvements at FM 2920. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid in the 1st quarter of 2010. (Last Updated On 10/20/2009) |
| Falvel Rd - 2 | FM 2920 | Spring Stuebner | 291Q | Proposed widening to a 4-lane concrete pavement with appropriate drainage system. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid in the 2nd quarter of 2010. (Last Updated On 10/20/2009) |
| FM 2100-Huffman New Caney | Wolf Rd | FM 1485 | 259N | Pursue alignment study and right of way mapping for ultimate 150-foot right of way. Project is currently in the study phase. (Last Updated On 8/19/2009) |
| Gosling Rd | Kuykendahl Rd | FM 2920 | 290V 290R | Proposed 2-lane asphalt roadway with combination storm sewer/ditch improvements between Kuykendahl Road and FM 2920. Joint participation project between Harris County and TxDOT. TxDOT is managing the construction activity that commenced on October 14, 2009. Construction completion is expected by April 24,2010 (barring any challenges beyond the Contractor's control, e.g., excessive inclement weather days). (Last Updated On 12/28/2009) |
| Grand Pkwy - F1 and F2 | IH 10 | US 59 | 445T | Proposed 4-lane divided roadway also known as SH 99. Managed by The Grand Parkway Association (GPA). For additional information contact GPA, at (713) 965-0871. (Last Updated On 8/17/2009) |
| Hollister Rd - 1 | Beltway 8 | W Greens Rd | 370V | Installation of a 4-lane concrete boulevard section with storm sewer system and offsite storm water detention. Project was awarded to Beyer Construction and is currently in the construction phase. Construction activity commenced September 21, 2009 and is scheduled for construction completion by July 18, 2010. (Last Updated On 12/29/2009) |
| Hollister Rd - 2 | W Greens Rd | Bourgeois Rd | 370M | Installation of a 4-lane concrete boulevard section with storm sewer system, traffic signalization on Hollister at Bourgeois and offsite storm water detention. Project was awarded to Beyer Construction and is currently in the construction phase. Construction activity commenced September 21, 2009 and is scheduled for construction completion by July 18, 2010. (Last Updated On 12/29/2009) |
| Hollister Rd - 3 | Bourgeois Rd | FM 1960 | 370G | Proposed 4-lane concrete boulevard section with storm sewer system and offsite storm water detention. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid in the fourth quarter of 2010. (Last Updated On 1/6/2010) |
| Holzwarth Rd | Meadow Edge Ln | FM 2920 | 292X | Proposed improvements include extending Holzwarth Road as 4-lane asphalt pavement within a 100' right of way including drainage mitigation, traffic signalization, signal modifications and fiber optic interconnect. Project is currently in the preliminary engineering phase. (Last Updated On 8/17/2009) |
| Hufsmith-Kohrville Rd | Spring Cypress Rd | FM 2920 | 329P 289E | Proposed alignment study and report for developing alignment options identifying the existing and projected land uses including existing drainage conditions, future drainage needs and right of way requirements for the recommended typical section. (Last Updated On 6/15/2009) |
| Imperial Valley Dr - A | N of Rankin Rd | 125' NW Remington Heights Dr | 372H | Proposed improvements include installation of the remaining half boulevard section. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid this section in the 1st Quarter of 2010. (Last Updated On 1/6/2010) |
| Imperial Valley Dr - B | 125 NW of Remington Heigh Dr | Airtex Dr | 372D | Proposed improvements include the installation of a 4-lane concrete boulevard section, storm sewer system, drainage mitigation and traffic control devices as warranted. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid this section in the 4th Quarter of 2010. (Last Updated On 12/29/2009) |
| Jones Rd - A | SH 290 | FM 529 | 409P | Proposed installation of 4-lane concrete boulevard section with storm sewer system, detention, railroad crossing and traffic signalization at US 290 and FM 529. Project is currently in the engineering design phase and our goal is to bid this project in the 1st quarter of 2010. (Last Updated On 12/29/2009) |
| Kuykendahl Rd - A | FM 2920 | Willow Creek | 290R | Widen from a 2-lane asphalt roadway to a 4-lane asphalt pavement with continuous left turn lane, combination roadside ditches and storm sewer system, bridge over Willow Creek, drainage mitigation and traffic signal modifications. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid in the 2nd quarter 2010. (Last Updated On 10/20/2009) |
| Kuykendahl Rd - B | Willow Creek | Augusta Pines Dr | 290A | Widen existing 2-lane asphalt roadway to a 4-lane asphalt pavement with continuous left turn lane, combination roadside ditches and storm sewer system, traffic signal at Hufsmith Road and traffic signal modifications. Project is currently in the engineering design phase and is expected to bid in the 1st quarter of 2010. (Last Updated On 9/14/2009) |
| Kuykendahl Rd - C | Augusta Pines Dr | Spring Creek Dr | 250S | Upgrade the existing 2-lane asphalt roadway to a combination 2-lane or 4-lane concrete pavement, treed medians, 4-foot unimproved shoulders with open ditches within a 160-foot right of way. This is a joint participation project between Harris County Precinct 4 and The Woodlands Road Utility District No.1. Harris County will fund $5.8 million of the construction cost. The Woodlands Road Utility District No.1 has agreed to provide engineering design and and fund construction costs exceeding Precinct 4's committment. Final design efforts are currently in progress and Harris County expects to obtain Commissioners' Court approval to bid the improvements in the 2nd quarter of 2010. (Last Updated On 1/6/2010) |
| Kuykendahl Rd at Louetta Rd | 331B | Intersection improvements (right turn lanes and modified left turn lanes) were completed on October 29, 2009. Additional improvements will include the deployment of a Changeable Lane Assignment Signal System (CLASS) at the intersection of Kuykendahl Road at Louetta Road. CLASS provides the ability to integrate operations between the traffic signal control system and the CLASS application allowing lane assignments to change with the traffic patterns for better intersection management. The CLASS installation is expected to begin in the second quarter of 2010. (Last Updated On 12/28/2009) | ||
| Lee Rd at FM 1960 | 334V | Proposed improvements include upgrading the Lee Road at FM 1960 intersection to two-concrete travel lanes in each direction including the southbound turn lane transition and associated storage bay. Currently in the engineering design phase. (Last Updated On 8/17/2009) | ||
| North Eldridge Pkwy | W Little York Rd | FM 529 | 408Z | Proposed improvements include installation of a continuous turn lane, appropriate drainage conveyance system, incorporation of dual northbound/southbound left turn lanes on North Eldridge Parkway at FM 529, including traffic signal and fiber optic interconnect modifications. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid this project in the 2nd quarter of 2010. (Last Updated On 12/29/2009) |
| North Eldridge Pkwy at West Little York Rd | 408Z | Intersection improvements (right turn lanes and modified left turn lanes) were completed on October 29, 2009. Additional improvements will include the deployment of a Changeable Lane Assignment Signal System (CLASS) at the intersection of North Eldridge and West Little York. CLASS provides the ability to integrate operations between the traffic signal control system and the CLASS application allowing lane assignments to change with the traffic patterns for better intersection management. The CLASS installation is expected to begin in the second quarter of 2010. (Last Updated On 12/28/2009) | ||
| Perry Rd - A | FM 1960 | North of Mills Rd | 369Q | Proposed improvements include widening from an existing 2-lane asphalt pavement with roadside ditches to a 4-lane concrete boulevard section with storm sewer system, offsite detention, and signalization at Lou Edd Road and Mills Road intersections. Project was awarded to Menade Construction and is currently in the construction phase. Construction activity will commence November 30, 2009 and is scheduled for construction completion by November 4, 2010. (Last Updated On 11/11/2009) |
| Perry Rd - B | Mills Rd | SH 249 | 369L | Proposed improvements include widening from an existing 2-lane asphalt pavement with roadside ditches to a 4-lane concrete boulevard section with storm sewer system and offsite detention. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid this project in the 2nd quarter of 2010. (Last Updated On 12/29/2009) |
| Red Oak Dr | FM 1960 | Drava Ln | 332J | Proposed improvements include upgrading the existing 2-lane asphalt roadway to a combination 3-lane or 4-lane concrete roadway with storm sewer system within a 60-foot right of way. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid this project in the 1st quarter of 2010. (Last Updated On 12/29/2009) |
| Spring Cypress Rd - A | Telge Rd | Faulkey Gully | 327Z | Proposed improvements include widening the existing 2-lane asphalt roadway to a 4-lane concrete boulevard section with storm sewer system, drainage mitigation and traffic signal modifications. Project is currently in the preliminary engineering phase. (Last Updated On 8/17/2009) |
| Spring Cypress Rd - B | Faulkey Gully | SH 249 | 328Q | Proposed improvements include widening the existing 2-lane asphalt roadway to a 4-lane concrete boulevard section with storm sewer system, drainage mitigation and traffic signal modifications. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid this project in the 4th quarter of 2010. (Last Updated On 1/6/2010) |
| Spring Stuebner Rd - A | Kuykendahl Rd | Rhodes Rd | 290L | Proposed improvements include widening the existing 2-lane asphalt pavement to a 4-lane concrete boulevard with storm sewer system, drainage mitigation, traffic signals or traffic signal modifications. Project is currently in the preliminary engineering phase. (Last Updated On 8/17/2009) |
| Spring Stuebner Rd - B | Rhodes Rd | Falvel Rd | 291J | Proposed improvements include widening the existing 2-lane asphalt pavement to a 4-lane concrete boulevard with storm sewer system, drainage mitigation, traffic signals or traffic signal modifications. Project is currently in the preliminary engineering phase. (Last Updated On 8/17/2009) |
| Spring Stuebner Rd - C | Falvel Rd | I45 | 291Q | Proposed improvements include widening the existing 2-lane asphalt pavement to a 4-lane concrete boulevard with storm sewer system, drainage mitigation, traffic signals or traffic signal modifications. Project is currently in the preliminary engineering phase. (Last Updated On 8/17/2009) |
| Stuebner Airline Rd - A | Spring Cypress Rd | Thora Ln | 330B | Proposed improvements including upgrading from a 2-lane asphalt pavement to a 5-lane concrete pavement section, drainage mitigation with combination storm sewer system, swale ditch and detention. Project is currently in the engineering design phase. (Last Updated On 1/13/2010) |
| Stuebner Airline Rd - B | Thora Ln | FM 2920 | 290W | Proposed improvements including upgrading from a 2-lane asphalt pavement to a 5-lane concrete pavement section, drainage mitigation with combination storm sewer system, swale ditch and detention. Project is currently in engineering design phase. (Last Updated On 1/13/2010) |
| TC Jester Blvd - A | N of Spears Rd | FM 1960 | 371C | Proposed installation of a 4-lane concrete boulevard section with storm sewer system and offsite detention. Project is currently in the preliminary engineering phase. (Last Updated On 8/17/2009) |
| TC Jester Blvd - C1 | Center Ct Dr | Spring Cypress Rd | 330D | TC Jester Boulevard was extended between Center Court Drive and Spring Cypress Road and project improvements included the realignment of Klein Cemetery Road including a traffic signal system on T.C. Jester Boulevard at Spring Cypress Road. Construction efforts have been completed and the corridor was opened to the traveling public on February 6, 2010. (Last Updated On 2/16/2010) |
| Tomball Outfall Ditch | Graham Dr | Barbara St | 288L | Proposed installation of a box culvert system and extreme event swales capable of conveying a 100 year rainfall event. Project was bid and will be managed by Harris County Flood Control District (HCFCD) in conjunction with HCFCD's M125 midreach and downstream improvements. Construction for this project began on June 22, 2009 and is scheduled to be complete by February 17, 2010. (Last Updated On 9/14/2009) |
| West Greens Rd - A B | SH 249 | Hollister Dr | 370R | Proposed 4-lane concrete boulevard, including storm sewer system, drainage outfall, storm water detention, bridge over Greens Bayou and BNRR track. Project is being designed and will be constructed in two segments; A) from east of SH 249 to Cutten Road and B) from Cutten Road to Hollister Road. Segment A is in the preliminary engineering phase and Segment B is in the engineering design phase. (Last Updated On 8/17/2009) |
| West Little York Rd at Guhn Rd | 410Y | TS&II 2007 Package VI includes (4) intersections: 1) West Little York at Guhn Road, 2) Atascocita at Atascocita Meadows, 3) Atascocita at Atasca Oaks Drive and 4) Will Clayton Parkway at Atascocita. Project is currently in the bidding phase for construction purposes. (Last Updated On 12/28/2009) | ||
| West Rd | Old Meadow Ln | Blacksmith Dr | 410G | Proposed installation of a 4-foot wide sidewalk on the south side of West Road between Old Meadow Lane and Blacksmith Drive. Project is currently in the engineering design phase. (Last Updated On 8/17/2009) |
| Will Clayton Pkwy - A | US 59 | S Houston Ave | 375C | Widen from the existing 2-lane asphalt pavement to a 5-lane asphalt pavement (2-lanes in each direction with a continuous turn lane) including a new bridge structure over the railroad tracks to accommodate westbound traffic. Project is currently in the engineering design phase and our goal is to bid this segment in the 1st quarter of 2010. (Last Updated On 12/29/2009) |
| Will Clayton Pkwy - B | S Houston Ave | Wilson Rd | 375D | Widen existing 2-lane roadway to a 5-lane asphalt pavement (2-lanes in each direction with a continuous turn lane). Project is currently in the bidding phase for construction purposes. (Last Updated On 12/29/2009) |
| Will Clayton Pkwy at Atascocita Rd | 376G | TS&II 2007 Package VI includes (4) intersections: 1) Will Clayton Parkway at Atascocita, 2) Atascocita at Atascocita Meadows, 3) Atascocita at Atasca Oaks Drive and 4) West Little York at Guhn Road. Project is currently in the bidding phase for construction purposes. (Last Updated On 12/28/2009) | ||
| Woodland Hills Dr | Woodland Path Dr | Will Clayton Pkwy | 376M | Proposed improvements include widening to a 4-lane concrete boulevard section. Project is currently in the engineering design phase and our goal is to request Commissioners' Court authorization to bid in the 1st quarter 2010. (Last Updated On 10/20/2009) |